Intersection nears completion

The intersection improvements at the corner
of Cedar Hills Boulevard and Barnes Road are finally back on track
after a short delay rumored to be caused by delays in the manufacture
of the signal poles.
The improvements are being done by Polygon Homes, builders
of the Timberland housing development on the former Teufel Nursery
property on Cornell. Polygon spokesperson Liz Holland says that the
project should be completed in April.
She says we may see some “temporary
lane closures for paving or putting down stripes but that would only
be between the hours of 9-3,” so it
shouldn’t even disturb your commute.
Improvements include an additional
right-turn lane on westbound Barnes, a new right-turn lane on eastbound
Barnes, and some widening in anticipation of an additional through lane on
westbound Barnes.
|